PRINCE2 PRINCE2 7 Practitioner Practice Test 56
Question 550
For this project-management problem, the team is comparing possible shortcuts: a freight routing program has emergency suppliers on paper but no evidence they can take over. Which proposed workaround should be REJECTED as unsafe? Select ONE answer.
- Prepare a justified exception plan to replace the affected approved baseline when authorized
- Assume a documented contingency always works without testing dependencies
- Assign project commercial management responsibilities and define how supplier commitments and changes are coordinated
- Assess upside opportunities alongside threats and plan proportionate exploitation or enhancement
Explanation
Correct Answer
B:The unsafe shortcut is to assume a documented contingency always works without testing dependencies. Naming a response strategy without implementation leaves the project exposed. The defensible response is instead to verify that risk responses are actionable, proportionate and integrated with plans, using the diagnostic step to inspect response triggers, resourcing, tests and any residual exposure before changing settings. Afterward, the team should confirm this result: Tested response arrangements address the defined risk event in realistic conditions. It must maintain the safeguard to exercise contingency plans and review residual risk at boundaries. By contrast, the response tied to this evidence is: Assume a documented contingency always works without testing dependencies.
Incorrect Answers
A:Prepare a justified exception plan to replace the affected approved baseline when authorized. The relevant authority approves a replacement baseline before exception delivery proceeds. Tested response arrangements address the defined risk event in realistic conditions. The shortcut most directly implicated here is: Assume a documented contingency always works without testing dependencies.
C:Assign project commercial management responsibilities and define how supplier commitments and changes are coordinated. Contracts and project governance must align so the board can control risk and value. Tested response arrangements address the defined risk event in realistic conditions. The shortcut most directly implicated here is: Assume a documented contingency always works without testing dependencies.
D:Assess upside opportunities alongside threats and plan proportionate exploitation or enhancement. The selected opportunity produces measurable value without violating risk tolerance. Tested response arrangements address the defined risk event in realistic conditions. The shortcut most directly implicated here is: Assume a documented contingency always works without testing dependencies.
Question 551
A project board needs to manage this condition: a food traceability project stores ambiguous risk titles without causes, owners or response dates. Which administrative action best resolves the specific control gap? Select ONE answer.
- Prioritize issues according to severity, product impact, urgency and approved tolerances
- Appoint senior user accountability for requirements, expected benefits and user acceptance
- Keep clear cause-event-effect descriptions, accountable owners and dated response status in the risk register
- Include measurable sustainability outcomes and material impacts in investment options and evaluation
Explanation
Correct Answer
C:First, check risk entry completeness and trace updates to evidence and decisions. Keep clear cause-event-effect descriptions, accountable owners and dated response status in the risk register. Risk records are useful when they support timely decisions and follow-through. Success requires: Decision-makers can understand exposure, response ownership and residual status from the register. Repeating review register accuracy and overdue actions throughout delivery helps prevent recurrence.
Incorrect Answers
A:Prioritize issues according to severity, product impact, urgency and approved tolerances. High-consequence issues are addressed or escalated before lower-impact work. Decision-makers can understand exposure, response ownership and residual status from the register.
B:Appoint senior user accountability for requirements, expected benefits and user acceptance. User needs and benefits are represented in acceptance decisions and board direction. Decision-makers can understand exposure, response ownership and residual status from the register.
D:Include measurable sustainability outcomes and material impacts in investment options and evaluation. The approved justification includes monitored sustainability indicators and credible tradeoffs. Decision-makers can understand exposure, response ownership and residual status from the register.
Question 552
An operations team is unsure why this occurred: a food traceability project stores ambiguous risk titles without causes, owners or response dates. Which targeted diagnostic step would produce the most relevant evidence? Select ONE answer.
- Compare team activities, deliverables and quality records against the authorized work package
- Compare available delivery capability against product requirements and supplier commitments
- Compare stakeholder complexity, risk and decision rights with the proposed team structure
- Check risk entry completeness and trace updates to evidence and decisions
Explanation
Correct Answer
D:The strongest first investigation is to check risk entry completeness and trace updates to evidence and decisions. Risk records are useful when they support timely decisions and follow-through. If that evidence confirms the issue, the team should keep clear cause-event-effect descriptions, accountable owners and dated response status in the risk register. A subsequent acceptance check should confirm this result: Decision-makers can understand exposure, response ownership and residual status from the register. This check produces evidence before any broad configuration change, avoiding the risky proposal to replace risk descriptions with unqualified red amber green colors alone.
Incorrect Answers
A:Compare team activities, deliverables and quality records against the authorized work package. Teams may plan work flexibly but cannot unilaterally change authorized product acceptance. Decision-makers can understand exposure, response ownership and residual status from the register. The relevant investigation is: Check risk entry completeness and trace updates to evidence and decisions.
B:Compare available delivery capability against product requirements and supplier commitments. Technical resource gaps are escalated through appropriate supplier governance. Decision-makers can understand exposure, response ownership and residual status from the register. The relevant investigation is: Check risk entry completeness and trace updates to evidence and decisions.
C:Compare stakeholder complexity, risk and decision rights with the proposed team structure. The structure is proportionate and still supports clear user, business and supplier decisions. Decision-makers can understand exposure, response ownership and residual status from the register. The relevant investigation is: Check risk entry completeness and trace updates to evidence and decisions.
Question 553
The senior user wants proof that this problem is resolved: a food traceability project stores ambiguous risk titles without causes, owners or response dates. Which end-to-end verification is most useful? Select ONE answer.
- Decision-makers can understand exposure, response ownership and residual status from the register
- A documented board choice reflects credible comparative value and explicit tradeoffs
- Approved benefit measures can be traced to users, data sources and review dates
- The risk register covers material exposures with described causes and impacts
Explanation
Correct Answer
A:A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to review register accuracy and overdue actions throughout delivery. The decisive acceptance evidence is this result: Decision-makers can understand exposure, response ownership and residual status from the register. Risk records are useful when they support timely decisions and follow-through. The operating team should diagnose it by checking whether it can check risk entry completeness and trace updates to evidence and decisions, then keep clear cause-event-effect descriptions, accountable owners and dated response status in the risk register where justified.
Incorrect Answers
B:A documented board choice reflects credible comparative value and explicit tradeoffs. Decision-makers can understand exposure, response ownership and residual status from the register.
C:Approved benefit measures can be traced to users, data sources and review dates. Decision-makers can understand exposure, response ownership and residual status from the register.
D:The risk register covers material exposures with described causes and impacts. Decision-makers can understand exposure, response ownership and residual status from the register.
Question 554
An incident has been closed after the team addressed this condition: a food traceability project stores ambiguous risk titles without causes, owners or response dates. Which follow-up control is most effective? Select ONE answer.
- Revisit issue priorities after new impact evidence arrives
- Review register accuracy and overdue actions throughout delivery
- Review supplier capacity and competence before each stage commitment
- Keep reporting evidence aligned with risks, issues and business case updates
Explanation
Correct Answer
B:It complements, rather than replaces, the immediate administrative action to keep clear cause-event-effect descriptions, accountable owners and dated response status in the risk register and diagnostic evidence to check risk entry completeness and trace updates to evidence and decisions. Periodic testing should confirm this result: Decision-makers can understand exposure, response ownership and residual status from the register. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to review register accuracy and overdue actions throughout delivery. Risk records are useful when they support timely decisions and follow-through.
Incorrect Answers
A:Revisit issue priorities after new impact evidence arrives. High-consequence issues are addressed or escalated before lower-impact work. Decision-makers can understand exposure, response ownership and residual status from the register. To avoid recurrence, review register accuracy and overdue actions throughout delivery.
C:Review supplier capacity and competence before each stage commitment. Technical resource gaps are escalated through appropriate supplier governance. Decision-makers can understand exposure, response ownership and residual status from the register. To avoid recurrence, review register accuracy and overdue actions throughout delivery.
D:Keep reporting evidence aligned with risks, issues and business case updates. The project board can decide continuation or recovery using a credible report. Decision-makers can understand exposure, response ownership and residual status from the register. To avoid recurrence, review register accuracy and overdue actions throughout delivery.
Question 555
For this project-management problem, the team is comparing possible shortcuts: a food traceability project stores ambiguous risk titles without causes, owners or response dates. Which proposed workaround should be REJECTED as unsafe? Select ONE answer.
- Appoint senior user accountability for requirements, expected benefits and user acceptance
- Update role descriptions, decision limits and interface responsibilities to match the current organization
- Replace risk descriptions with unqualified red amber green colors alone
- Arrange board-delegated business, user and supplier assurance independent of day-to-day management
Explanation
Correct Answer
C:The unsafe shortcut is to replace risk descriptions with unqualified red amber green colors alone. Risk records are useful when they support timely decisions and follow-through. The defensible response is instead to keep clear cause-event-effect descriptions, accountable owners and dated response status in the risk register, using the diagnostic step to check risk entry completeness and trace updates to evidence and decisions before changing settings. Afterward, the team should confirm this result: Decision-makers can understand exposure, response ownership and residual status from the register. It must maintain the safeguard to review register accuracy and overdue actions throughout delivery.
Incorrect Answers
A:Appoint senior user accountability for requirements, expected benefits and user acceptance. User needs and benefits are represented in acceptance decisions and board direction. Decision-makers can understand exposure, response ownership and residual status from the register. The shortcut most directly implicated here is: Replace risk descriptions with unqualified red amber green colors alone.
B:Update role descriptions, decision limits and interface responsibilities to match the current organization. Each major decision and delivery obligation maps to a competent accountable role. Decision-makers can understand exposure, response ownership and residual status from the register. The shortcut most directly implicated here is: Replace risk descriptions with unqualified red amber green colors alone.
D:Arrange board-delegated business, user and supplier assurance independent of day-to-day management. The board receives objective challenge and evidence without confusing assurance and management. Decision-makers can understand exposure, response ownership and residual status from the register. The shortcut most directly implicated here is: Replace risk descriptions with unqualified red amber green colors alone.
Question 556
During a PRINCE2 management-stage review, the team encounters this situation: a public health analytics program closes risks after workshops with no reassessment history. What is the most appropriate controlled response? Select ONE answer.
- Record planned and completed quality activities, outcomes and defects against products
- Compare realistic options including do nothing using costs, benefits, risk and sustainability impacts
- Assign project commercial management responsibilities and define how supplier commitments and changes are coordinated
- Keep clear cause-event-effect descriptions, accountable owners and dated response status in the risk register
Explanation
Correct Answer
D:First, check risk entry completeness and trace updates to evidence and decisions. Keep clear cause-event-effect descriptions, accountable owners and dated response status in the risk register. Risk records are useful when they support timely decisions and follow-through. Success requires: Decision-makers can understand exposure, response ownership and residual status from the register. Repeating review register accuracy and overdue actions throughout delivery helps prevent recurrence. By contrast, the response tied to this evidence is: Keep clear cause-event-effect descriptions, accountable owners and dated response status in the risk register.
Incorrect Answers
A:Record planned and completed quality activities, outcomes and defects against products. The quality register identifies who tested what, when, and with what outcome. Decision-makers can understand exposure, response ownership and residual status from the register.
B:Compare realistic options including do nothing using costs, benefits, risk and sustainability impacts. A documented board choice reflects credible comparative value and explicit tradeoffs. Decision-makers can understand exposure, response ownership and residual status from the register.
C:Assign project commercial management responsibilities and define how supplier commitments and changes are coordinated. Contracts and project governance must align so the board can control risk and value. Decision-makers can understand exposure, response ownership and residual status from the register.
Question 557
The project management team is troubleshooting this situation: a public health analytics program closes risks after workshops with no reassessment history. Which check isolates the likely operating dependency? Select ONE answer.
- Check risk entry completeness and trace updates to evidence and decisions
- Compare issue consequences and deadlines with agreed acceptance and business priorities
- Compare project board composition against those who will use and benefit from outputs
- Inspect acceptance records, benefits plan baselines and responsible business roles
Explanation
Correct Answer
A:The strongest first investigation is to check risk entry completeness and trace updates to evidence and decisions. Risk records are useful when they support timely decisions and follow-through. If that evidence confirms the issue, the team should keep clear cause-event-effect descriptions, accountable owners and dated response status in the risk register. A subsequent acceptance check should confirm this result: Decision-makers can understand exposure, response ownership and residual status from the register. This check produces evidence before any broad configuration change, avoiding the risky proposal to replace risk descriptions with unqualified red amber green colors alone. By contrast, the response tied to this evidence is: Check risk entry completeness and trace updates to evidence and decisions.
Incorrect Answers
B:Compare issue consequences and deadlines with agreed acceptance and business priorities. High-consequence issues are addressed or escalated before lower-impact work. Decision-makers can understand exposure, response ownership and residual status from the register. The relevant investigation is: Check risk entry completeness and trace updates to evidence and decisions.
C:Compare project board composition against those who will use and benefit from outputs. User needs and benefits are represented in acceptance decisions and board direction. Decision-makers can understand exposure, response ownership and residual status from the register. The relevant investigation is: Check risk entry completeness and trace updates to evidence and decisions.
D:Inspect acceptance records, benefits plan baselines and responsible business roles. Handover records identify accountable owners and scheduled benefit reviews after closure. Decision-makers can understand exposure, response ownership and residual status from the register. The relevant investigation is: Check risk entry completeness and trace updates to evidence and decisions.
Question 558
An administrator claims the following problem is resolved: a public health analytics program closes risks after workshops with no reassessment history. Which measured outcome confirms that claim? Select ONE answer.
- The project applies consistent quality controls with retained objective review evidence
- Decision-makers can understand exposure, response ownership and residual status from the register
- Approved benefit measures can be traced to users, data sources and review dates
- Issue decisions are formally recorded at the right governance level
Explanation
Correct Answer
B:A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to review register accuracy and overdue actions throughout delivery. The decisive acceptance evidence is this result: Decision-makers can understand exposure, response ownership and residual status from the register. Risk records are useful when they support timely decisions and follow-through. The operating team should diagnose it by checking whether it can check risk entry completeness and trace updates to evidence and decisions, then keep clear cause-event-effect descriptions, accountable owners and dated response status in the risk register where justified. By contrast, the response tied to this evidence is: Decision-makers can understand exposure, response ownership and residual status from the register.
Incorrect Answers
A:The project applies consistent quality controls with retained objective review evidence. Decision-makers can understand exposure, response ownership and residual status from the register.
C:Approved benefit measures can be traced to users, data sources and review dates. Decision-makers can understand exposure, response ownership and residual status from the register. The operating team should diagnose it by checking whether it can check risk entry completeness and trace updates to evidence and decisions, then keep clear cause-event-effect descriptions, accountable owners and dated response status in the risk register where justified.
D:Issue decisions are formally recorded at the right governance level. Decision-makers can understand exposure, response ownership and residual status from the register.
Question 559
After resolving the following issue, the operations team wants to prevent a recurrence: a public health analytics program closes risks after workshops with no reassessment history. Which ongoing control is best? Select ONE answer.
- Update product-based plans when scope or dependencies change
- Check cost assumptions regularly and escalate predicted breaches against tolerance
- Review register accuracy and overdue actions throughout delivery
- Review the quality approach as products, suppliers or regulatory demands change
Explanation
Correct Answer
C:It complements, rather than replaces, the immediate administrative action to keep clear cause-event-effect descriptions, accountable owners and dated response status in the risk register and diagnostic evidence to check risk entry completeness and trace updates to evidence and decisions. Periodic testing should confirm this result: Decision-makers can understand exposure, response ownership and residual status from the register. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to review register accuracy and overdue actions throughout delivery. Risk records are useful when they support timely decisions and follow-through. By contrast, the response tied to this evidence is: Review register accuracy and overdue actions throughout delivery.
Incorrect Answers
A:Update product-based plans when scope or dependencies change. The plan covers required products in a logical sequence with explicit quality expectations. Decision-makers can understand exposure, response ownership and residual status from the register. To avoid recurrence, review register accuracy and overdue actions throughout delivery.
B:Check cost assumptions regularly and escalate predicted breaches against tolerance. The board considers a transparent forecast with affordable funding and defensible benefits. Decision-makers can understand exposure, response ownership and residual status from the register. To avoid recurrence, review register accuracy and overdue actions throughout delivery.
D:Review the quality approach as products, suppliers or regulatory demands change. The project applies consistent quality controls with retained objective review evidence. Decision-makers can understand exposure, response ownership and residual status from the register. To avoid recurrence, review register accuracy and overdue actions throughout delivery.
Question 560
A project manager is under pressure to address the following issue quickly: a public health analytics program closes risks after workshops with no reassessment history. Which proposal creates the clearest avoidable risk? Select ONE answer.
- Allocate suitable quality assurance and approval roles with appropriate independence and competence
- Use checkpoint evidence to produce stage-level highlight reporting appropriate to each authority
- Refresh life-cycle costs, assumptions and the investment justification before requesting commitment
- Replace risk descriptions with unqualified red amber green colors alone
Explanation
Correct Answer
D:The unsafe shortcut is to replace risk descriptions with unqualified red amber green colors alone. Risk records are useful when they support timely decisions and follow-through. The defensible response is instead to keep clear cause-event-effect descriptions, accountable owners and dated response status in the risk register, using the diagnostic step to check risk entry completeness and trace updates to evidence and decisions before changing settings. Afterward, the team should confirm this result: Decision-makers can understand exposure, response ownership and residual status from the register. It must maintain the safeguard to review register accuracy and overdue actions throughout delivery. By contrast, the response tied to this evidence is: Replace risk descriptions with unqualified red amber green colors alone.
Incorrect Answers
A:Allocate suitable quality assurance and approval roles with appropriate independence and competence. Reliable quality decisions depend on credible review responsibility and evidence. Decision-makers can understand exposure, response ownership and residual status from the register. The shortcut most directly implicated here is: Replace risk descriptions with unqualified red amber green colors alone.
B:Use checkpoint evidence to produce stage-level highlight reporting appropriate to each authority. Team-level progress supports accurate board-facing stage summaries. Decision-makers can understand exposure, response ownership and residual status from the register. The shortcut most directly implicated here is: Replace risk descriptions with unqualified red amber green colors alone.
C:Refresh life-cycle costs, assumptions and the investment justification before requesting commitment. The board considers a transparent forecast with affordable funding and defensible benefits. Decision-makers can understand exposure, response ownership and residual status from the register. The shortcut most directly implicated here is: Replace risk descriptions with unqualified red amber green colors alone.