PRINCE2 PRINCE2 7 Practitioner Practice Test 37
Question 360
A project manager is under pressure to address the following issue quickly: a mobile healthcare pilot has several delivery teams using incompatible definitions of its final product. Which proposal creates the clearest avoidable risk? Select ONE answer.
- Organize a prepared quality review with agreed criteria, roles, issue logging and follow-up
- Define benefits, owners, measurement timing and dependencies in the updated business case and benefits management approach
- Identify and manage internal and external product dependencies in the appropriate plans
- Declare the product complete when the development team reports all tasks done
Explanation
Correct Answer
D:The unsafe shortcut is to declare the product complete when the development team reports all tasks done. A shared definition of the final product anchors planning and handover. The defensible response is instead to define overall project product composition, customer quality expectations and acceptance methods, using the diagnostic step to compare project outcomes with the agreed overall product description and user expectations before changing settings. Afterward, the team should confirm this result: The final project output can be tested against clearly approved acceptance criteria. It must maintain the safeguard to keep the project product description aligned with authorized changes. By contrast, the response tied to this evidence is: Declare the product complete when the development team reports all tasks done.
Incorrect Answers
A:Organize a prepared quality review with agreed criteria, roles, issue logging and follow-up. The product is accepted only after recorded issues are handled and criteria demonstrated. The final project output can be tested against clearly approved acceptance criteria. The shortcut most directly implicated here is: Declare the product complete when the development team reports all tasks done.
B:Define benefits, owners, measurement timing and dependencies in the updated business case and benefits management approach. Approved benefit measures can be traced to users, data sources and review dates. The final project output can be tested against clearly approved acceptance criteria. The shortcut most directly implicated here is: Declare the product complete when the development team reports all tasks done.
C:Identify and manage internal and external product dependencies in the appropriate plans. Upstream products are accepted before dependent work is committed beyond tolerance. The final project output can be tested against clearly approved acceptance criteria. The shortcut most directly implicated here is: Declare the product complete when the development team reports all tasks done.
Question 361
During a PRINCE2 management-stage review, the team encounters this situation: a utility replacement project writes a week-by-week plan for uncertain work three years away but omits next-month tasks. What is the most appropriate controlled response? Select ONE answer.
- Detail the immediate management stage while keeping longer-term project planning at appropriate summary level
- Reassess continuing desirability, viability and achievability before approval of the changed commitment
- Use a proportionate outline business case and project brief to support initiation, then develop the full justification
- Identify threats and opportunities across objectives, stakeholders, sustainability and delivery dependencies
Explanation
Correct Answer
A:First, inspect stage product dependencies, assumptions, resource estimates and tolerances. Detail the immediate management stage while keeping longer-term project planning at appropriate summary level. Progressive planning avoids false precision while preserving staged governance. Success means the next stage has a realistic plan approved by the appropriate authority. Repeating re-estimate each succeeding stage with fresh delivery information helps prevent recurrence.
Incorrect Answers
B:Reassess continuing desirability, viability and achievability before approval of the changed commitment. A formal continue, adjust or stop decision is backed by the current business case. The next stage has a realistic plan approved by the appropriate authority.
C:Use a proportionate outline business case and project brief to support initiation, then develop the full justification. Initiation is authorized on a credible brief while the full business case is developed before delivery commitment. The next stage has a realistic plan approved by the appropriate authority.
D:Identify threats and opportunities across objectives, stakeholders, sustainability and delivery dependencies. The risk register covers material exposures with described causes and impacts. The next stage has a realistic plan approved by the appropriate authority.
Question 362
The project management team is troubleshooting this situation: a utility replacement project writes a week-by-week plan for uncertain work three years away but omits next-month tasks. Which check isolates the likely operating dependency? Select ONE answer.
- Inspect assurance mandates and conflicts of interest against project delivery responsibilities
- Inspect stage product dependencies, assumptions, resource estimates and tolerances
- Compare delivered products and support materials with approved acceptance and transition criteria
- Compare team activities, deliverables and quality records against the authorized work package
Explanation
Correct Answer
B:The strongest first investigation is to inspect stage product dependencies, assumptions, resource estimates and tolerances. Progressive planning avoids false precision while preserving staged governance. If that evidence confirms the issue, the team should detail the immediate management stage while keeping longer-term project planning at appropriate summary level. A subsequent acceptance check should confirm this result: The next stage has a realistic plan approved by the appropriate authority. This check produces evidence before any broad configuration change, avoiding the risky proposal to use the original whole-project plan as a substitute for every stage plan.
Incorrect Answers
A:Inspect assurance mandates and conflicts of interest against project delivery responsibilities. The board receives objective challenge and evidence without confusing assurance and management. The next stage has a realistic plan approved by the appropriate authority. The relevant investigation is: Inspect stage product dependencies, assumptions, resource estimates and tolerances.
C:Compare delivered products and support materials with approved acceptance and transition criteria. Receiving owners confirm the product is acceptable and usable in live operations. The next stage has a realistic plan approved by the appropriate authority. The relevant investigation is: Inspect stage product dependencies, assumptions, resource estimates and tolerances.
D:Compare team activities, deliverables and quality records against the authorized work package. Teams may plan work flexibly but cannot unilaterally change authorized product acceptance. The next stage has a realistic plan approved by the appropriate authority. The relevant investigation is: Inspect stage product dependencies, assumptions, resource estimates and tolerances.
Question 363
An administrator claims the following problem is resolved: a utility replacement project writes a week-by-week plan for uncertain work three years away but omits next-month tasks. Which measured outcome confirms that claim? Select ONE answer.
- Material responses are implemented and monitored by identifiable responsible people
- Team-level progress supports accurate board-facing stage summaries
- The next stage has a realistic plan approved by the appropriate authority
- Reviewers can consistently determine whether each delivered product meets the approved criteria
Explanation
Correct Answer
C:A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to re-estimate each succeeding stage with fresh delivery information. The decisive acceptance evidence is this result: The next stage has a realistic plan approved by the appropriate authority. Progressive planning avoids false precision while preserving staged governance. The operating team should diagnose it by checking whether it can inspect stage product dependencies, assumptions, resource estimates and tolerances, then detail the immediate management stage while keeping longer-term project planning at appropriate summary level where justified.
Incorrect Answers
A:Material responses are implemented and monitored by identifiable responsible people. The next stage has a realistic plan approved by the appropriate authority.
B:Team-level progress supports accurate board-facing stage summaries. The next stage has a realistic plan approved by the appropriate authority.
D:Reviewers can consistently determine whether each delivered product meets the approved criteria. Quality expectations must become testable acceptance evidence. The next stage has a realistic plan approved by the appropriate authority.
Question 364
After resolving the following issue, the operations team wants to prevent a recurrence: a utility replacement project writes a week-by-week plan for uncertain work three years away but omits next-month tasks. Which ongoing control is best? Select ONE answer.
- Exercise contingency plans and review residual risk at boundaries
- Review board membership and delegated authority when sponsorship changes
- Keep reporting evidence aligned with risks, issues and business case updates
- Re-estimate each succeeding stage with fresh delivery information
Explanation
Correct Answer
D:It complements, rather than replaces, the immediate administrative action to detail the immediate management stage while keeping longer-term project planning at appropriate summary level and diagnostic evidence to inspect stage product dependencies, assumptions, resource estimates and tolerances. Periodic testing should confirm this result: The next stage has a realistic plan approved by the appropriate authority. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to re-estimate each succeeding stage with fresh delivery information. Progressive planning avoids false precision while preserving staged governance.
Incorrect Answers
A:Exercise contingency plans and review residual risk at boundaries. Tested response arrangements address the defined risk event in realistic conditions. The next stage has a realistic plan approved by the appropriate authority. To avoid recurrence, re-estimate each succeeding stage with fresh delivery information.
B:Review board membership and delegated authority when sponsorship changes. The executive provides a single point of business accountability. The next stage has a realistic plan approved by the appropriate authority. To avoid recurrence, re-estimate each succeeding stage with fresh delivery information.
C:Keep reporting evidence aligned with risks, issues and business case updates. The project board can decide continuation or recovery using a credible report. The next stage has a realistic plan approved by the appropriate authority. To avoid recurrence, re-estimate each succeeding stage with fresh delivery information.
Question 365
A project manager is under pressure to address the following issue quickly: a utility replacement project writes a week-by-week plan for uncertain work three years away but omits next-month tasks. Which proposal creates the clearest avoidable risk? Select ONE answer.
- Use the original whole-project plan as a substitute for every stage plan
- Use checkpoint evidence to produce stage-level highlight reporting appropriate to each authority
- Tailor progress controls to risk and scale while preserving evidence, delegated authority and exception escalation
- Scale the project management structure proportionately while preserving necessary governance interests and roles
Explanation
Correct Answer
A:The unsafe shortcut is to use the original whole-project plan as a substitute for every stage plan. Progressive planning avoids false precision while preserving staged governance. The defensible response is instead to detail the immediate management stage while keeping longer-term project planning at appropriate summary level, using the diagnostic step to inspect stage product dependencies, assumptions, resource estimates and tolerances before changing settings. Afterward, the team should confirm this result: The next stage has a realistic plan approved by the appropriate authority. It must maintain the safeguard to re-estimate each succeeding stage with fresh delivery information.
Incorrect Answers
B:Use checkpoint evidence to produce stage-level highlight reporting appropriate to each authority. Team-level progress supports accurate board-facing stage summaries. The next stage has a realistic plan approved by the appropriate authority. The shortcut most directly implicated here is: Use the original whole-project plan as a substitute for every stage plan.
C:Tailor progress controls to risk and scale while preserving evidence, delegated authority and exception escalation. Reporting is proportionate yet produces reliable forecasts and clear authority decisions. The next stage has a realistic plan approved by the appropriate authority. The shortcut most directly implicated here is: Use the original whole-project plan as a substitute for every stage plan.
D:Scale the project management structure proportionately while preserving necessary governance interests and roles. The structure is proportionate and still supports clear user, business and supplier decisions. The next stage has a realistic plan approved by the appropriate authority. The shortcut most directly implicated here is: Use the original whole-project plan as a substitute for every stage plan.
Question 366
A project delivery team reports that a factory automation stage starts without credible product dependencies or risk-adjusted estimates. Which action directly addresses the issue? Select ONE answer.
- Update role descriptions, decision limits and interface responsibilities to match the current organization
- Detail the immediate management stage while keeping longer-term project planning at appropriate summary level
- Monitor projected end position and escalate likely tolerance breaches before they occur
- Reassess continuing desirability, viability and achievability before approval of the changed commitment
Explanation
Correct Answer
B:First, inspect stage product dependencies, assumptions, resource estimates and tolerances. Detail the immediate management stage while keeping longer-term project planning at appropriate summary level. The reported operational condition is that a factory automation stage starts without credible product dependencies or risk-adjusted estimates. Progressive planning avoids false precision while preserving staged governance. Success means the next stage has a realistic plan approved by the appropriate authority. Repeating re-estimate each succeeding stage with fresh delivery information helps prevent recurrence.
Incorrect Answers
A:Update role descriptions, decision limits and interface responsibilities to match the current organization. Each major decision and delivery obligation maps to a competent accountable role. Progressive planning avoids false precision while preserving staged governance.
C:Monitor projected end position and escalate likely tolerance breaches before they occur. The relevant authority receives an exception forecast before delegation limits are exceeded. Progressive planning avoids false precision while preserving staged governance.
D:Reassess continuing desirability, viability and achievability before approval of the changed commitment. A formal continue, adjust or stop decision is backed by the current business case. Progressive planning avoids false precision while preserving staged governance.
Question 367
An administrator wants to identify the failure before making a change: a factory automation stage starts without credible product dependencies or risk-adjusted estimates. Which inspection is the most informative? Select ONE answer.
- Compare opportunity assumptions, probability and benefit with the current business case
- Compare forecast deviation with delegated tolerance and the options available to recover
- Inspect stage product dependencies, assumptions, resource estimates and tolerances
- Compare consolidated exposure and latest forecasts with stage and project risk tolerances
Explanation
Correct Answer
C:The strongest first investigation is to inspect stage product dependencies, assumptions, resource estimates and tolerances. Progressive planning avoids false precision while preserving staged governance. If that evidence confirms the issue, the team should detail the immediate management stage while keeping longer-term project planning at appropriate summary level. A subsequent acceptance check should confirm this result: The next stage has a realistic plan approved by the appropriate authority. This check produces evidence before any broad configuration change, avoiding the risky proposal to use the original whole-project plan as a substitute for every stage plan. By contrast, the response tied to this evidence is: Inspect stage product dependencies, assumptions, resource estimates and tolerances.
Incorrect Answers
A:Compare opportunity assumptions, probability and benefit with the current business case. The selected opportunity produces measurable value without violating risk tolerance. Progressive planning avoids false precision while preserving staged governance. The relevant investigation is: Inspect stage product dependencies, assumptions, resource estimates and tolerances.
B:Compare forecast deviation with delegated tolerance and the options available to recover. The relevant authority approves a replacement baseline before exception delivery proceeds. Progressive planning avoids false precision while preserving staged governance. The relevant investigation is: Inspect stage product dependencies, assumptions, resource estimates and tolerances.
D:Compare consolidated exposure and latest forecasts with stage and project risk tolerances. Risk governance requires clear boundaries between routine response and exception. Progressive planning avoids false precision while preserving staged governance. The relevant investigation is: Inspect stage product dependencies, assumptions, resource estimates and tolerances.
Question 368
After a controlled change, the team needs to resolve this report: a factory automation stage starts without credible product dependencies or risk-adjusted estimates. Which observable result would best establish success? Select ONE answer.
- Approvers receive traceable options and a credible impact statement
- Commercial decisions support project objectives and have traceable approval evidence
- The risk register covers material exposures with described causes and impacts
- The next stage has a realistic plan approved by the appropriate authority
Explanation
Correct Answer
D:A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to re-estimate each succeeding stage with fresh delivery information. The decisive acceptance evidence is this result: The next stage has a realistic plan approved by the appropriate authority. Progressive planning avoids false precision while preserving staged governance. The operating team should diagnose it by checking whether it can inspect stage product dependencies, assumptions, resource estimates and tolerances, then detail the immediate management stage while keeping longer-term project planning at appropriate summary level where justified. By contrast, the response tied to this evidence is: The next stage has a realistic plan approved by the appropriate authority.
Incorrect Answers
A:Approvers receive traceable options and a credible impact statement. Change control protects overall project viability rather than only the altered feature. Progressive planning avoids false precision while preserving staged governance. Success in this case requires: The next stage has a realistic plan approved by the appropriate authority.
B:Commercial decisions support project objectives and have traceable approval evidence. Contracts and project governance must align so the board can control risk and value. Progressive planning avoids false precision while preserving staged governance. Success in this case requires: The next stage has a realistic plan approved by the appropriate authority.
C:The risk register covers material exposures with described causes and impacts. Progressive planning avoids false precision while preserving staged governance. Success in this case requires: The next stage has a realistic plan approved by the appropriate authority.
Question 369
A project assurance reviewer sees a pattern in this report: a factory automation stage starts without credible product dependencies or risk-adjusted estimates. Which recurring safeguard should remain in force? Select ONE answer.
- Re-estimate each succeeding stage with fresh delivery information
- Track exception assumptions and renewed tolerances after authorization
- Revalidate benefit forecasts and their owners when scope and usage assumptions change
- Include support-readiness reviews in future product handovers
Explanation
Correct Answer
A:It complements, rather than replaces, the immediate administrative action to detail the immediate management stage while keeping longer-term project planning at appropriate summary level and diagnostic evidence to inspect stage product dependencies, assumptions, resource estimates and tolerances. Periodic testing should confirm this result: The next stage has a realistic plan approved by the appropriate authority. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to re-estimate each succeeding stage with fresh delivery information. Progressive planning avoids false precision while preserving staged governance. By contrast, the response tied to this evidence is: Re-estimate each succeeding stage with fresh delivery information.
Incorrect Answers
B:Track exception assumptions and renewed tolerances after authorization. The relevant authority approves a replacement baseline before exception delivery proceeds. Progressive planning avoids false precision while preserving staged governance. To avoid recurrence, re-estimate each succeeding stage with fresh delivery information.
C:Revalidate benefit forecasts and their owners when scope and usage assumptions change. Approved benefit measures can be traced to users, data sources and review dates. Progressive planning avoids false precision while preserving staged governance. To avoid recurrence, re-estimate each succeeding stage with fresh delivery information.
D:Include support-readiness reviews in future product handovers. Receiving owners confirm the product is acceptable and usable in live operations. Progressive planning avoids false precision while preserving staged governance. To avoid recurrence, re-estimate each succeeding stage with fresh delivery information.
Question 370
A team wants to simplify its response to this situation: a factory automation stage starts without credible product dependencies or risk-adjusted estimates. Which shortcut is the LEAST defensible? Select ONE answer.
- Prioritize issues according to severity, product impact, urgency and approved tolerances
- Use the original whole-project plan as a substitute for every stage plan
- Define quality responsibilities, standards, methods and records in the tailored quality management approach
- Verify that risk responses are actionable, proportionate and integrated with plans
Explanation
Correct Answer
B:The unsafe shortcut is to use the original whole-project plan as a substitute for every stage plan. Progressive planning avoids false precision while preserving staged governance. The defensible response is instead to detail the immediate management stage while keeping longer-term project planning at appropriate summary level, using the diagnostic step to inspect stage product dependencies, assumptions, resource estimates and tolerances before changing settings. Afterward, the team should confirm this result: The next stage has a realistic plan approved by the appropriate authority. It must maintain the safeguard to re-estimate each succeeding stage with fresh delivery information. By contrast, the response tied to this evidence is: Use the original whole-project plan as a substitute for every stage plan.
Incorrect Answers
A:Prioritize issues according to severity, product impact, urgency and approved tolerances. High-consequence issues are addressed or escalated before lower-impact work. Progressive planning avoids false precision while preserving staged governance. The shortcut most directly implicated here is: Use the original whole-project plan as a substitute for every stage plan.
C:Define quality responsibilities, standards, methods and records in the tailored quality management approach. The project applies consistent quality controls with retained objective review evidence. Progressive planning avoids false precision while preserving staged governance. The shortcut most directly implicated here is: Use the original whole-project plan as a substitute for every stage plan.
D:Verify that risk responses are actionable, proportionate and integrated with plans. Tested response arrangements address the defined risk event in realistic conditions. Progressive planning avoids false precision while preserving staged governance. The shortcut most directly implicated here is: Use the original whole-project plan as a substitute for every stage plan.