PRINCE2 PRINCE2 7 Practitioner Practice Test 12
Question 110
A project manager is under pressure to address the following issue quickly: a local government analytics program faces opposition from residents whose concerns were not identified during planning. Which proposal creates the clearest avoidable risk? Select ONE answer.
- Facilitate role-based tradeoff decisions grounded in the agreed product outcomes and acceptance criteria
- Send identical launch emails to executives and end users instead of engaging affected groups
- Combine leadership on purpose and team engagement with clear management of responsibilities and controls
- Address the cause of resistance through listening, agreed change support and clear leadership
Explanation
Correct Answer
B:The unsafe shortcut is to send identical launch emails to executives and end users instead of engaging affected groups. Successful adoption depends on identifying and working with people affected by the project's products. The defensible response is instead to map affected stakeholders and develop proportionate two-way engagement tailored to influence and impact, using the diagnostic step to compare stakeholder analysis with groups actually affected and evidence of concerns or participation before changing settings. Afterward, the team should confirm this result: Engagement records show relevant perspectives reflected in decisions and communication approaches. It must maintain the safeguard to refresh stakeholder analysis and engagement activities after major changes. By contrast, the response tied to this evidence is: Send identical launch emails to executives and end users instead of engaging affected groups.
Incorrect Answers
A:Facilitate role-based tradeoff decisions grounded in the agreed product outcomes and acceptance criteria. An authorized decision records accepted tradeoffs and a testable product-quality outcome. Engagement records show relevant perspectives reflected in decisions and communication approaches. The shortcut most directly implicated here is: Send identical launch emails to executives and end users instead of engaging affected groups.
C:Combine leadership on purpose and team engagement with clear management of responsibilities and controls. Team members understand the purpose and execute owned deliverables with visible escalation routes. Engagement records show relevant perspectives reflected in decisions and communication approaches. The shortcut most directly implicated here is: Send identical launch emails to executives and end users instead of engaging affected groups. It must maintain the safeguard to refresh stakeholder analysis and engagement activities after major changes.
D:Address the cause of resistance through listening, agreed change support and clear leadership. Affected groups understand the change and demonstrate readiness through observed practice. Engagement records show relevant perspectives reflected in decisions and communication approaches. The shortcut most directly implicated here is: Send identical launch emails to executives and end users instead of engaging affected groups. It must maintain the safeguard to refresh stakeholder analysis and engagement activities after major changes.
Question 111
During a PRINCE2 management-stage review, the team encounters this situation: a municipal permitting team resists new workflow because prior promised training was never delivered. What is the most appropriate controlled response? Select ONE answer.
- Map affected stakeholders and develop proportionate two-way engagement tailored to influence and impact
- Assign accountable communication owners and test comprehension for affected audiences
- Address the cause of resistance through listening, agreed change support and clear leadership
- Combine leadership on purpose and team engagement with clear management of responsibilities and controls
Explanation
Correct Answer
C:First, collect frontline feedback and compare perceived impacts with the change management approach. Address the cause of resistance through listening, agreed change support and clear leadership. Change leadership requires understanding people and practical adoption impacts, not only schedules. Success requires: Affected groups understand the change and demonstrate readiness through observed practice. Repeating track sentiment and adoption barriers through staged transition activities helps prevent recurrence.
Incorrect Answers
A:Map affected stakeholders and develop proportionate two-way engagement tailored to influence and impact. Engagement records show relevant perspectives reflected in decisions and communication approaches. Affected groups understand the change and demonstrate readiness through observed practice.
B:Assign accountable communication owners and test comprehension for affected audiences. Two-way communication is a controlled management activity rather than a one-off announcement. Affected groups understand the change and demonstrate readiness through observed practice.
D:Combine leadership on purpose and team engagement with clear management of responsibilities and controls. Team members understand the purpose and execute owned deliverables with visible escalation routes. Affected groups understand the change and demonstrate readiness through observed practice.
Question 112
The project management team is troubleshooting this situation: a municipal permitting team resists new workflow because prior promised training was never delivered. Which check isolates the likely operating dependency? Select ONE answer.
- Inspect cross-team handoff failures, decision latency and task ownership
- Trace the disputed demands to senior user needs, supplier capability and approved constraints
- Map communication needs against audience roles, decisions and the current communication management approach
- Collect frontline feedback and compare perceived impacts with the change management approach
Explanation
Correct Answer
D:The strongest first investigation is to collect frontline feedback and compare perceived impacts with the change management approach. Change leadership requires understanding people and practical adoption impacts, not only schedules. If that evidence confirms the issue, the team should address the cause of resistance through listening, agreed change support and clear leadership. A subsequent acceptance check should confirm this result: Affected groups understand the change and demonstrate readiness through observed practice. This check produces evidence before any broad configuration change, avoiding the risky proposal to silence objections by excluding affected users from change meetings.
Incorrect Answers
A:Inspect cross-team handoff failures, decision latency and task ownership. Handoffs consistently meet defined quality criteria and unresolved dependencies surface promptly. Affected groups understand the change and demonstrate readiness through observed practice. The relevant investigation is: Collect frontline feedback and compare perceived impacts with the change management approach.
B:Trace the disputed demands to senior user needs, supplier capability and approved constraints. An authorized decision records accepted tradeoffs and a testable product-quality outcome. Affected groups understand the change and demonstrate readiness through observed practice. The relevant investigation is: Collect frontline feedback and compare perceived impacts with the change management approach.
C:Map communication needs against audience roles, decisions and the current communication management approach. The right audience receives actionable information in a usable form and on time. Affected groups understand the change and demonstrate readiness through observed practice. The relevant investigation is: Collect frontline feedback and compare perceived impacts with the change management approach.
Question 113
An administrator claims the following problem is resolved: a municipal permitting team resists new workflow because prior promised training was never delivered. Which measured outcome confirms that claim? Select ONE answer.
- Affected groups understand the change and demonstrate readiness through observed practice
- An authorized decision records accepted tradeoffs and a testable product-quality outcome
- Team members understand the purpose and execute owned deliverables with visible escalation routes
- Engagement records show relevant perspectives reflected in decisions and communication approaches
Explanation
Correct Answer
A:A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to track sentiment and adoption barriers through staged transition activities. The decisive acceptance evidence is this result: Affected groups understand the change and demonstrate readiness through observed practice. Change leadership requires understanding people and practical adoption impacts, not only schedules. The operating team should diagnose it by checking whether it can collect frontline feedback and compare perceived impacts with the change management approach, then address the cause of resistance through listening, agreed change support and clear leadership where justified.
Incorrect Answers
B:An authorized decision records accepted tradeoffs and a testable product-quality outcome. Affected groups understand the change and demonstrate readiness through observed practice.
C:Team members understand the purpose and execute owned deliverables with visible escalation routes. Affected groups understand the change and demonstrate readiness through observed practice.
D:Engagement records show relevant perspectives reflected in decisions and communication approaches. Affected groups understand the change and demonstrate readiness through observed practice.
Question 114
After resolving the following issue, the operations team wants to prevent a recurrence: a municipal permitting team resists new workflow because prior promised training was never delivered. Which ongoing control is best? Select ONE answer.
- Review team health and management behaviors at retrospective and governance checkpoints
- Track sentiment and adoption barriers through staged transition activities
- Refresh stakeholder analysis and engagement activities after major changes
- Review remote working practices and dependency maps as participants change
Explanation
Correct Answer
B:It complements, rather than replaces, the immediate administrative action to address the cause of resistance through listening, agreed change support and clear leadership and diagnostic evidence to collect frontline feedback and compare perceived impacts with the change management approach. Periodic testing should confirm this result: Affected groups understand the change and demonstrate readiness through observed practice. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to track sentiment and adoption barriers through staged transition activities. Change leadership requires understanding people and practical adoption impacts, not only schedules.
Incorrect Answers
A:Review team health and management behaviors at retrospective and governance checkpoints. People are more likely to surface problems when leadership combines safety with responsibility. Affected groups understand the change and demonstrate readiness through observed practice. To avoid recurrence, track sentiment and adoption barriers through staged transition activities.
C:Refresh stakeholder analysis and engagement activities after major changes. Engagement records show relevant perspectives reflected in decisions and communication approaches. Affected groups understand the change and demonstrate readiness through observed practice. To avoid recurrence, track sentiment and adoption barriers through staged transition activities.
D:Review remote working practices and dependency maps as participants change. Handoffs consistently meet defined quality criteria and unresolved dependencies surface promptly. Affected groups understand the change and demonstrate readiness through observed practice. To avoid recurrence, track sentiment and adoption barriers through staged transition activities.
Question 115
A project manager is under pressure to address the following issue quickly: a municipal permitting team resists new workflow because prior promised training was never delivered. Which proposal creates the clearest avoidable risk? Select ONE answer.
- Facilitate role-based tradeoff decisions grounded in the agreed product outcomes and acceptance criteria
- Build psychological safety, transparent accountability and collaborative problem solving
- Silence objections by excluding affected users from change meetings
- Tailor message, channel, timing and owner to each decision-maker and affected group
Explanation
Correct Answer
C:The unsafe shortcut is to silence objections by excluding affected users from change meetings. Change leadership requires understanding people and practical adoption impacts, not only schedules. The defensible response is instead to address the cause of resistance through listening, agreed change support and clear leadership, using the diagnostic step to collect frontline feedback and compare perceived impacts with the change management approach before changing settings. Afterward, the team should confirm this result: Affected groups understand the change and demonstrate readiness through observed practice. It must maintain the safeguard to track sentiment and adoption barriers through staged transition activities.
Incorrect Answers
A:Facilitate role-based tradeoff decisions grounded in the agreed product outcomes and acceptance criteria. An authorized decision records accepted tradeoffs and a testable product-quality outcome. Affected groups understand the change and demonstrate readiness through observed practice. The shortcut most directly implicated here is: Silence objections by excluding affected users from change meetings.
B:Build psychological safety, transparent accountability and collaborative problem solving. People are more likely to surface problems when leadership combines safety with responsibility. Affected groups understand the change and demonstrate readiness through observed practice. The shortcut most directly implicated here is: Silence objections by excluding affected users from change meetings.
D:Tailor message, channel, timing and owner to each decision-maker and affected group. The right audience receives actionable information in a usable form and on time. Affected groups understand the change and demonstrate readiness through observed practice. The shortcut most directly implicated here is: Silence objections by excluding affected users from change meetings.
Question 116
A project delivery team reports that a manufacturing scheduling team fears job redesign but leadership labels questions as simple disobedience. Which action directly addresses the issue? Select ONE answer.
- Assess people impacts and create a measurable readiness and transition baseline
- Tailor message, channel, timing and owner to each decision-maker and affected group
- Build psychological safety, transparent accountability and collaborative problem solving
- Address the cause of resistance through listening, agreed change support and clear leadership
Explanation
Correct Answer
D:First, collect frontline feedback and compare perceived impacts with the change management approach. Address the cause of resistance through listening, agreed change support and clear leadership. The reported operational condition is that a manufacturing scheduling team fears job redesign but leadership labels questions as simple disobedience. Change leadership requires understanding people and practical adoption impacts, not only schedules. Success requires: Affected groups understand the change and demonstrate readiness through observed practice. Repeating track sentiment and adoption barriers through staged transition activities helps prevent recurrence.
Incorrect Answers
A:Assess people impacts and create a measurable readiness and transition baseline. Training and role-transition evidence shows users can perform the intended new work. Change leadership requires understanding people and practical adoption impacts, not only schedules.
B:Tailor message, channel, timing and owner to each decision-maker and affected group. The right audience receives actionable information in a usable form and on time. Change leadership requires understanding people and practical adoption impacts, not only schedules.
C:Build psychological safety, transparent accountability and collaborative problem solving. People are more likely to surface problems when leadership combines safety with responsibility. Change leadership requires understanding people and practical adoption impacts, not only schedules.
Question 117
An administrator wants to identify the failure before making a change: a manufacturing scheduling team fears job redesign but leadership labels questions as simple disobedience. Which inspection is the most informative? Select ONE answer.
- Collect frontline feedback and compare perceived impacts with the change management approach
- Trace the disputed demands to senior user needs, supplier capability and approved constraints
- Compare stakeholder analysis with groups actually affected and evidence of concerns or participation
- Check channel reach, feedback and decision records against the communication management approach
Explanation
Correct Answer
A:The strongest first investigation is to collect frontline feedback and compare perceived impacts with the change management approach. Change leadership requires understanding people and practical adoption impacts, not only schedules. If that evidence confirms the issue, the team should address the cause of resistance through listening, agreed change support and clear leadership. A subsequent acceptance check should confirm this result: Affected groups understand the change and demonstrate readiness through observed practice. This check produces evidence before any broad configuration change, avoiding the risky proposal to silence objections by excluding affected users from change meetings. By contrast, the response tied to this evidence is: Collect frontline feedback and compare perceived impacts with the change management approach.
Incorrect Answers
B:Trace the disputed demands to senior user needs, supplier capability and approved constraints. An authorized decision records accepted tradeoffs and a testable product-quality outcome. Change leadership requires understanding people and practical adoption impacts, not only schedules. The relevant investigation is: Collect frontline feedback and compare perceived impacts with the change management approach.
C:Compare stakeholder analysis with groups actually affected and evidence of concerns or participation. Engagement records show relevant perspectives reflected in decisions and communication approaches. Change leadership requires understanding people and practical adoption impacts, not only schedules. The relevant investigation is: Collect frontline feedback and compare perceived impacts with the change management approach.
D:Check channel reach, feedback and decision records against the communication management approach. Two-way communication is a controlled management activity rather than a one-off announcement. Change leadership requires understanding people and practical adoption impacts, not only schedules. The relevant investigation is: Collect frontline feedback and compare perceived impacts with the change management approach.
Question 118
After a controlled change, the team needs to resolve this report: a manufacturing scheduling team fears job redesign but leadership labels questions as simple disobedience. Which observable result would best establish success? Select ONE answer.
- Handoffs consistently meet defined quality criteria and unresolved dependencies surface promptly
- Affected groups understand the change and demonstrate readiness through observed practice
- The right audience receives actionable information in a usable form and on time
- An authorized decision records accepted tradeoffs and a testable product-quality outcome
Explanation
Correct Answer
B:A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to track sentiment and adoption barriers through staged transition activities. The decisive acceptance evidence is this result: Affected groups understand the change and demonstrate readiness through observed practice. Change leadership requires understanding people and practical adoption impacts, not only schedules. The operating team should diagnose it by checking whether it can collect frontline feedback and compare perceived impacts with the change management approach, then address the cause of resistance through listening, agreed change support and clear leadership where justified. By contrast, the response tied to this evidence is: Affected groups understand the change and demonstrate readiness through observed practice.
Incorrect Answers
A:Handoffs consistently meet defined quality criteria and unresolved dependencies surface promptly. Change leadership requires understanding people and practical adoption impacts, not only schedules. Success in this case requires: Affected groups understand the change and demonstrate readiness through observed practice.
C:The right audience receives actionable information in a usable form and on time. Change leadership requires understanding people and practical adoption impacts, not only schedules. Success in this case requires: Affected groups understand the change and demonstrate readiness through observed practice.
D:An authorized decision records accepted tradeoffs and a testable product-quality outcome. Change leadership requires understanding people and practical adoption impacts, not only schedules. Success in this case requires: Affected groups understand the change and demonstrate readiness through observed practice.
Question 119
A project assurance reviewer sees a pattern in this report: a manufacturing scheduling team fears job redesign but leadership labels questions as simple disobedience. Which recurring safeguard should remain in force? Select ONE answer.
- Review team health and management behaviors at retrospective and governance checkpoints
- Monitor feedback and refine messages throughout implementation
- Track sentiment and adoption barriers through staged transition activities
- Review remote working practices and dependency maps as participants change
Explanation
Correct Answer
C:It complements, rather than replaces, the immediate administrative action to address the cause of resistance through listening, agreed change support and clear leadership and diagnostic evidence to collect frontline feedback and compare perceived impacts with the change management approach. Periodic testing should confirm this result: Affected groups understand the change and demonstrate readiness through observed practice. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to track sentiment and adoption barriers through staged transition activities. Change leadership requires understanding people and practical adoption impacts, not only schedules. By contrast, the response tied to this evidence is: Track sentiment and adoption barriers through staged transition activities.
Incorrect Answers
A:Review team health and management behaviors at retrospective and governance checkpoints. People are more likely to surface problems when leadership combines safety with responsibility. Change leadership requires understanding people and practical adoption impacts, not only schedules. To avoid recurrence, track sentiment and adoption barriers through staged transition activities.
B:Monitor feedback and refine messages throughout implementation. Two-way communication is a controlled management activity rather than a one-off announcement. Change leadership requires understanding people and practical adoption impacts, not only schedules. To avoid recurrence, track sentiment and adoption barriers through staged transition activities.
D:Review remote working practices and dependency maps as participants change. Handoffs consistently meet defined quality criteria and unresolved dependencies surface promptly. Change leadership requires understanding people and practical adoption impacts, not only schedules. To avoid recurrence, track sentiment and adoption barriers through staged transition activities.
Question 120
A team wants to simplify its response to this situation: a manufacturing scheduling team fears job redesign but leadership labels questions as simple disobedience. Which shortcut is the LEAST defensible? Select ONE answer.
- Map affected stakeholders and develop proportionate two-way engagement tailored to influence and impact
- Assess people impacts and create a measurable readiness and transition baseline
- Tailor message, channel, timing and owner to each decision-maker and affected group
- Silence objections by excluding affected users from change meetings
Explanation
Correct Answer
D:The unsafe shortcut is to silence objections by excluding affected users from change meetings. Change leadership requires understanding people and practical adoption impacts, not only schedules. The defensible response is instead to address the cause of resistance through listening, agreed change support and clear leadership, using the diagnostic step to collect frontline feedback and compare perceived impacts with the change management approach before changing settings. Afterward, the team should confirm this result: Affected groups understand the change and demonstrate readiness through observed practice. It must maintain the safeguard to track sentiment and adoption barriers through staged transition activities. By contrast, the response tied to this evidence is: Silence objections by excluding affected users from change meetings.
Incorrect Answers
A:Map affected stakeholders and develop proportionate two-way engagement tailored to influence and impact. Engagement records show relevant perspectives reflected in decisions and communication approaches. Change leadership requires understanding people and practical adoption impacts, not only schedules. The shortcut most directly implicated here is: Silence objections by excluding affected users from change meetings.
B:Assess people impacts and create a measurable readiness and transition baseline. Training and role-transition evidence shows users can perform the intended new work. Change leadership requires understanding people and practical adoption impacts, not only schedules. The shortcut most directly implicated here is: Silence objections by excluding affected users from change meetings.
C:Tailor message, channel, timing and owner to each decision-maker and affected group. The right audience receives actionable information in a usable form and on time. Change leadership requires understanding people and practical adoption impacts, not only schedules. The shortcut most directly implicated here is: Silence objections by excluding affected users from change meetings.