Question 680
A bank wants extra transaction reports but has not assessed whether they extend the vendor contract or launch date. Which result BEST demonstrates that the project-management response met the stated need?
Explanation
Correct Answer
The decision authority receives documented alternatives and impacts, and the request is not implemented while undecided. This is an observable measure of the intended outcome, not just evidence that a meeting or configuration occurred. A formal project change starts with a recorded request and impact assessment, not an immediate undocumented edit to the baseline. Situation: A bank wants extra transaction reports but has not assessed whether they extend the vendor contract or launch date.
Incorrect Answers
High-priority exposures have review dates, justified response owners, and contingency triggers rather than being treated as current defects. That outcome tests Qualitative risk probability and impact; it is not proof of this particular requirement. The more specific validation is: The decision authority receives documented alternatives and impacts, and the request is not implemented while undecided. Situation: A bank wants extra transaction reports but has not assessed whether they extend the vendor contract or launch date.
Incoming tasks move through visible states without overloaded in-progress columns and flow time becomes more predictable. That outcome tests Kanban flow versus sprint commitments; it is not proof of this particular requirement. The more specific validation is: The decision authority receives documented alternatives and impacts, and the request is not implemented while undecided. Situation: A bank wants extra transaction reports but has not assessed whether they extend the vendor contract or launch date.
Only approved extensions appear in the work plan, while rejected or deferred requests remain visible but uncommitted. That outcome tests Scope creep and baseline integrity; it is not proof of this particular requirement. The more specific validation is: The decision authority receives documented alternatives and impacts, and the request is not implemented while undecided. Situation: A bank wants extra transaction reports but has not assessed whether they extend the vendor contract or launch date.