Question 590
A sprint retrospective produces ideas but no owner follows through on improvement actions. Which project-management response BEST addresses the stated need?
Explanation
Correct Answer
Publish a focused agenda, assign facilitator and scribe, timebox discussion, and capture decisions with owners and due dates. This targets the specific project decision. Meeting effectiveness depends on outcomes and follow-through, not on attendance or duration alone. Before committing, assess: Review meeting purpose, participant roles, agenda, prior actions, unresolved decisions, and meeting minutes distribution. Situation: A sprint retrospective produces ideas but no owner follows through on improvement actions.
Incorrect Answers
Facilitate expectations, address role confusion, and establish collaboration norms as a newly assembled team moves from storming toward norming. That response is associated with Team stages and constructive conflict and does not directly settle this case. Its relevant principle is: Teams often pass forming, storming, norming and performing stages; managed conflict can improve cohesion but ignoring it blocks progress. The stated case instead calls for: Publish a focused agenda, assign facilitator and scribe, timebox discussion, and capture decisions with owners and due dates. Situation: A sprint retrospective produces ideas but no owner follows through on improvement actions.
Record an active issue, evaluate its severity and urgency, assign a resolver, and escalate it through the agreed path when thresholds are met. That response is associated with Issue severity triage and escalation and does not directly settle this case. Its relevant principle is: An issue is an existing impediment requiring action; its escalation priority reflects actual business impact rather than only theoretical risk. The stated case instead calls for: Publish a focused agenda, assign facilitator and scribe, timebox discussion, and capture decisions with owners and due dates. Situation: A sprint retrospective produces ideas but no owner follows through on improvement actions.
Map task precedence and identify the longest dependency path to forecast the earliest achievable finish before compressing work. That response is associated with Critical path and hard dependencies and does not directly settle this case. Its relevant principle is: The critical path is the longest duration path through dependent tasks; delaying a critical task can delay completion even if other tasks have slack. The stated case instead calls for: Publish a focused agenda, assign facilitator and scribe, timebox discussion, and capture decisions with owners and due dates. Situation: A sprint retrospective produces ideas but no owner follows through on improvement actions.