Question 50
A sprint planner needs a coherent goal and stable high-priority items after the previous sprint missed its forecast. Which result BEST demonstrates that the project-management response met the stated need?
Explanation
Correct Answer
The sprint goal fits actual capacity and accepted stories meet the definition of done rather than being counted merely because started. This is an observable measure of the intended outcome, not just evidence that a meeting or configuration occurred. Story points reflect relative complexity or effort rather than guaranteed hours, and an epic is too broad to treat as one small task. Situation: A sprint planner needs a coherent goal and stable high-priority items after the previous sprint missed its forecast.
Incorrect Answers
High-priority exposures have review dates, justified response owners, and contingency triggers rather than being treated as current defects. That outcome tests Qualitative risk probability and impact; it is not proof of this particular requirement. The more specific validation is: The sprint goal fits actual capacity and accepted stories meet the definition of done rather than being counted merely because started. Situation: A sprint planner needs a coherent goal and stable high-priority items after the previous sprint missed its forecast.
Forecasts show actual variance and buffer use transparently; authorized baseline changes retain a traceable reason and date. That outcome tests Schedule buffer and controlled rebaseline; it is not proof of this particular requirement. The more specific validation is: The sprint goal fits actual capacity and accepted stories meet the definition of done rather than being counted merely because started. Situation: A sprint planner needs a coherent goal and stable high-priority items after the previous sprint missed its forecast.
Each project has approved resource availability and staffing conflicts no longer appear as unexplained missed tasks. That outcome tests Matrix organization and resource conflicts; it is not proof of this particular requirement. The more specific validation is: The sprint goal fits actual capacity and accepted stories meet the definition of done rather than being counted merely because started. Situation: A sprint planner needs a coherent goal and stable high-priority items after the previous sprint missed its forecast.