Question 440
A branch rollout has a single internet carrier and must plan for a possible delivery delay. Before acting, which evidence should the project team examine FIRST to assess the stated need?
Explanation
Correct Answer
Inspect assumptions, supplier dependencies, architectural unknowns, exposure ratings, and contingency funding. This checks the relevant condition before the team intervenes. Risk management begins before problems occur; a risk register should be living and include mitigation and contingency ownership. The controlled response is: Identify plausible uncertainties during planning, score their potential impact, assign owners, and define response triggers before execution. Situation: A branch rollout has a single internet carrier and must plan for a possible delivery delay.
Incorrect Answers
Inspect approved-vendor records, current statement of work, contract expiration, procurement limits, and supplier capabilities. That evidence would investigate Vendor eligibility and existing contracts, not the main uncertainty in this situation. To decide the current case, examine: Inspect assumptions, supplier dependencies, architectural unknowns, exposure ratings, and contingency funding. Situation: A branch rollout has a single internet carrier and must plan for a possible delivery delay.
Review sponsor expectations, desired outcomes, preliminary deliverables, funding boundaries, and success metrics. That evidence would investigate Project charter and measurable success criteria, not the main uncertainty in this situation. To decide the current case, examine: Inspect assumptions, supplier dependencies, architectural unknowns, exposure ratings, and contingency funding. Situation: A branch rollout has a single internet carrier and must plan for a possible delivery delay.
Inspect estimated task duration, external deliverables, technical sequence, resource availability, and milestone acceptance criteria. That evidence would investigate Planning milestones and predecessor sequencing, not the main uncertainty in this situation. To decide the current case, examine: Inspect assumptions, supplier dependencies, architectural unknowns, exposure ratings, and contingency funding. Situation: A branch rollout has a single internet carrier and must plan for a possible delivery delay.