Question 1180
A company sends a spreadsheet attachment to twenty people and receives incompatible versions back. Which project-management response BEST addresses the stated need?
Explanation
Correct Answer
Use a controlled multi-author document repository with revision history and access permissions for distributed project plans. This targets the specific project decision. Real-time coauthoring improves collaboration, but source-of-truth versioning and document access rules remain necessary. Before committing, assess: Inspect editing permissions, document version history, simultaneous changes, approval process, and link-sharing scope. Situation: A company sends a spreadsheet attachment to twenty people and receives incompatible versions back.
Incorrect Answers
Use a burndown or burnup chart and past delivery velocity to forecast remaining work while accounting for changing scope. That response is associated with Agile burnup burndown and velocity interpretation and does not directly settle this case. Its relevant principle is: Burndown tracks work remaining and burnup tracks delivered work versus total scope; velocity describes prior throughput, not a guaranteed future commitment. The stated case instead calls for: Use a controlled multi-author document repository with revision history and access permissions for distributed project plans. Situation: A company sends a spreadsheet attachment to twenty people and receives incompatible versions back.
Use a control chart with a time-ordered process measure and control limits to distinguish routine variation from unusual process behavior. That response is associated with Control chart variation monitoring and does not directly settle this case. Its relevant principle is: Control charts assess process stability against statistical control limits; specification thresholds and control limits are not automatically identical. The stated case instead calls for: Use a controlled multi-author document repository with revision history and access permissions for distributed project plans. Situation: A company sends a spreadsheet attachment to twenty people and receives incompatible versions back.
Use a ticketing system with status, ownership, priority, resolution history, and escalation tracking for operational and project defects. That response is associated with Ticketing and case management workflow and does not directly settle this case. Its relevant principle is: Ticket systems manage discrete actionable requests and incidents; an informal mailbox alone lacks reliable assignment and status controls. The stated case instead calls for: Use a controlled multi-author document repository with revision history and access permissions for distributed project plans. Situation: A company sends a spreadsheet attachment to twenty people and receives incompatible versions back.