Question 1150
A university portal replacement adds two vendors and needs to align deliverables, dependencies, and first decision dates. Which TWO complementary steps provide the best response AND its necessary supporting assessment? Select TWO.
Explanation
Correct Answers
Review sponsor-approved charter, preliminary milestones, stakeholder list, team assignments, and decision protocol. This checks the relevant condition before the team intervenes. A kickoff creates shared understanding at initiation; it does not by itself prove final design approval or detailed execution readiness. The controlled response is: Hold a structured project kickoff to align objectives, roles, boundaries, communication methods, and immediate next actions. It complements the associated implementation step. Situation: A university portal replacement adds two vendors and needs to align deliverables, dependencies, and first decision dates.
Hold a structured project kickoff to align objectives, roles, boundaries, communication methods, and immediate next actions. This targets the specific project decision. A kickoff creates shared understanding at initiation; it does not by itself prove final design approval or detailed execution readiness. Before committing, assess: Review sponsor-approved charter, preliminary milestones, stakeholder list, team assignments, and decision protocol. It complements the associated assessment evidence. Situation: A university portal replacement adds two vendors and needs to align deliverables, dependencies, and first decision dates.
Incorrect Answers
The initial risk register connects top threats to owned treatments and is reviewed as new information arises. This is useful for Initial risk register and response planning but is not one of the complementary steps for this case. The appropriate paired decision combines: Hold a structured project kickoff to align objectives, roles, boundaries, communication methods, and immediate next actions. and Review sponsor-approved charter, preliminary milestones, stakeholder list, team assignments, and decision protocol. Situation: A university portal replacement adds two vendors and needs to align deliverables, dependencies, and first decision dates.
Inspect estimated task duration, external deliverables, technical sequence, resource availability, and milestone acceptance criteria. This is useful for Planning milestones and predecessor sequencing but is not one of the complementary steps for this case. The appropriate paired decision combines: Hold a structured project kickoff to align objectives, roles, boundaries, communication methods, and immediate next actions. and Review sponsor-approved charter, preliminary milestones, stakeholder list, team assignments, and decision protocol. Situation: A university portal replacement adds two vendors and needs to align deliverables, dependencies, and first decision dates.
Create a RACI matrix identifying the person responsible for doing work, one accountable owner for each key decision, and consulted or informed parties. This is useful for RACI responsibility assignment but is not one of the complementary steps for this case. The appropriate paired decision combines: Hold a structured project kickoff to align objectives, roles, boundaries, communication methods, and immediate next actions. and Review sponsor-approved charter, preliminary milestones, stakeholder list, team assignments, and decision protocol. Situation: A university portal replacement adds two vendors and needs to align deliverables, dependencies, and first decision dates.