CompTIA 220-1202 Practice Test 5
Question 40
At Brookfield Education, an office needs a supported Windows feature upgrade. Evidence: Installed business apps and profiles should remain intact. The support goal is to assess compatibility and perform a supported in-place upgrade. What operational signal should the support team monitor for regression or a return of the issue?
- Track firmware boot entry changes
- Monitor post-upgrade driver regressions
- Monitor imaging failures and duplicate identifiers
- Track unsupported hardware and blocked feature updates
Explanation
Correct Answer
B:
Monitor post-upgrade driver regressions. The case states that installed business apps and profiles should remain intact. In the monitor stage, this action directly supports the required outcome: assess compatibility and perform a supported in-place upgrade.
Incorrect Answers
A:
Monitor firmware boot entry changes. That step targets GPT and UEFI installation when the installer is booted in legacy mode and will not use the intended layout. The current situation instead says installed business apps and profiles should remain intact, and the goal is to assess compatibility and perform a supported in-place upgrade.
C:
Monitor imaging failures and duplicate identifiers. That step targets network imaging deployment when individual USB installations are inefficient and inconsistent. The current situation instead says installed business apps and profiles should remain intact, and the goal is to assess compatibility and perform a supported in-place upgrade.
D:
Track unsupported hardware and blocked feature updates. That step targets hardware compatibility upgrade gate when firmware and TPM capabilities differ across machines. The current situation instead says installed business apps and profiles should remain intact, and the goal is to assess compatibility and perform a supported in-place upgrade.
Question 41
At Crownridge Travel, a school needs identical baseline PCs in many classrooms. Evidence: Individual USB installations are inefficient and inconsistent. The support goal is to use approved network imaging or deployment automation. The technician must identify the likely cause before changing configuration or user data. Which first investigation best establishes what is wrong?
- Inspect TPM status, UEFI settings, RAM and CPU compatibility
- Inspect hardware model consistency and PXE/network reachability
- Determine backup completeness and installation media authenticity
- Check firmware boot mode and existing partition scheme
Explanation
Correct Answer
B:
Inspect hardware model consistency and PXE/network reachability. The case states that individual USB installations are inefficient and inconsistent. In the diagnose stage, this action directly supports the required outcome: use approved network imaging or deployment automation.
Incorrect Answers
A:
Inspect TPM status, UEFI settings, RAM and CPU compatibility. That step targets hardware compatibility upgrade gate when firmware and TPM capabilities differ across machines. The current situation instead says individual USB installations are inefficient and inconsistent, and the goal is to use approved network imaging or deployment automation.
C:
Determine backup completeness and installation media authenticity. That step targets clean installation versus upgrade when unknown software persists and system files cannot be trusted. The current situation instead says individual USB installations are inefficient and inconsistent, and the goal is to use approved network imaging or deployment automation.
D:
Check firmware boot mode and existing partition scheme. That step targets GPT and UEFI installation when the installer is booted in legacy mode and will not use the intended layout. The current situation instead says individual USB installations are inefficient and inconsistent, and the goal is to use approved network imaging or deployment automation.
Question 42
At Clearwater Public Works, a school needs identical baseline PCs in many classrooms. Evidence: Individual USB installations are inefficient and inconsistent. The support goal is to use approved network imaging or deployment automation. Which corrective or preventative action best addresses this requirement while retaining appropriate access and change controls?
- Use supported upgrade media with backup and rollback plan
- Boot approved media in UEFI mode and initialize GPT after backup
- Build a sysprepped standardized image with authorized deployment
- Perform a clean install after preserving user data and licensing
Explanation
Correct Answer
C:
Build a sysprepped standardized image with authorized deployment. The case states that individual USB installations are inefficient and inconsistent. In the design stage, this action directly supports the required outcome: use approved network imaging or deployment automation.
Incorrect Answers
A:
Use supported upgrade media with backup and rollback plan. That step targets in-place upgrade continuity when installed business apps and profiles should remain intact. The current situation instead says individual USB installations are inefficient and inconsistent, and the goal is to use approved network imaging or deployment automation.
B:
Boot approved media in UEFI mode and initialize GPT after backup. That step targets GPT and UEFI installation when the installer is booted in legacy mode and will not use the intended layout. The current situation instead says individual USB installations are inefficient and inconsistent, and the goal is to use approved network imaging or deployment automation.
D:
Perform a clean install after preserving user data and licensing. That step targets clean installation versus upgrade when unknown software persists and system files cannot be trusted. The current situation instead says individual USB installations are inefficient and inconsistent, and the goal is to use approved network imaging or deployment automation.
Question 43
At Atlas Technology, a school needs identical baseline PCs in many classrooms. Evidence: Individual USB installations are inefficient and inconsistent. The support goal is to use approved network imaging or deployment automation. Which bounded nonproduction test best checks the proposed solution before wider deployment?
- Upgrade one pilot computer with sample line-of-business apps
- Carry out the vendor compatibility checker on sample machines
- Reimage an isolated test PC and restore mock user files
- Deploy a golden image to several disposable lab endpoints
Explanation
Correct Answer
D:
Deploy a golden image to several disposable lab endpoints. The case states that individual USB installations are inefficient and inconsistent. In the pilot stage, this action directly supports the required outcome: use approved network imaging or deployment automation.
Incorrect Answers
A:
Upgrade one pilot computer with sample line-of-business apps. That step targets in-place upgrade continuity when installed business apps and profiles should remain intact. The current situation instead says individual USB installations are inefficient and inconsistent, and the goal is to use approved network imaging or deployment automation.
B:
Run the vendor compatibility checker on sample machines. That step targets hardware compatibility upgrade gate when firmware and TPM capabilities differ across machines. The current situation instead says individual USB installations are inefficient and inconsistent, and the goal is to use approved network imaging or deployment automation.
C:
Reimage an isolated test PC and restore mock user files. That step targets clean installation versus upgrade when unknown software persists and system files cannot be trusted. The current situation instead says individual USB installations are inefficient and inconsistent, and the goal is to use approved network imaging or deployment automation.
Question 44
At Redwood Healthcare, a school needs identical baseline PCs in many classrooms. Evidence: Individual USB installations are inefficient and inconsistent. The support goal is to use approved network imaging or deployment automation. Which result would most convincingly show the support requirement has been satisfied?
- Apps and profiles work and update completes without data loss
- Only supported devices proceed and backup is intact
- Clients receive distinct identities and required drivers
- No old unauthorized application remains after installation
Explanation
Correct Answer
C:
Clients receive distinct identities and required drivers. The case states that individual USB installations are inefficient and inconsistent. In the validate stage, this action directly supports the required outcome: use approved network imaging or deployment automation.
Incorrect Answers
A:
Apps and profiles work and update completes without data loss. That step targets in-place upgrade continuity when installed business apps and profiles should remain intact. The current situation instead says individual USB installations are inefficient and inconsistent, and the goal is to use approved network imaging or deployment automation.
B:
Only supported devices proceed and backup is intact. That step targets hardware compatibility upgrade gate when firmware and TPM capabilities differ across machines. The current situation instead says individual USB installations are inefficient and inconsistent, and the goal is to use approved network imaging or deployment automation.
D:
No old unauthorized application remains after installation. That step targets clean installation versus upgrade when unknown software persists and system files cannot be trusted. The current situation instead says individual USB installations are inefficient and inconsistent, and the goal is to use approved network imaging or deployment automation.
Question 45
At Lakeview Utilities, a school needs identical baseline PCs in many classrooms. Evidence: Individual USB installations are inefficient and inconsistent. The support goal is to use approved network imaging or deployment automation. What operational signal should the support team monitor for regression or a return of the issue?
- Monitor imaging failures and duplicate identifiers
- Watch redeployment errors and restore failures
- Monitor firmware boot entry changes
- Monitor post-upgrade driver regressions
Explanation
Correct Answer
A:
Monitor imaging failures and duplicate identifiers. The case states that individual USB installations are inefficient and inconsistent. In the monitor stage, this action directly supports the required outcome: use approved network imaging or deployment automation.
Incorrect Answers
B:
Watch redeployment errors and restore failures. That step targets clean installation versus upgrade when unknown software persists and system files cannot be trusted. The current situation instead says individual USB installations are inefficient and inconsistent, and the goal is to use approved network imaging or deployment automation.
C:
Monitor firmware boot entry changes. That step targets GPT and UEFI installation when the installer is booted in legacy mode and will not use the intended layout. The current situation instead says individual USB installations are inefficient and inconsistent, and the goal is to use approved network imaging or deployment automation.
D:
Monitor post-upgrade driver regressions. That step targets in-place upgrade continuity when installed business apps and profiles should remain intact. The current situation instead says individual USB installations are inefficient and inconsistent, and the goal is to use approved network imaging or deployment automation.
Question 46
At Briarfield Foods, a desktop cannot enable a newer Windows release. Evidence: Firmware and TPM capabilities differ across machines. The support goal is to check eligibility before forcing an unsupported OS build. The technician must identify the likely cause before changing configuration or user data. Which first investigation best establishes what is wrong?
- Review hardware model consistency and PXE/network reachability
- Inspect TPM status, UEFI settings, RAM and CPU compatibility
- Determine backup completeness and installation media authenticity
- Check firmware boot mode and existing partition scheme
Explanation
Correct Answer
B:
Inspect TPM status, UEFI settings, RAM and CPU compatibility. The case states that firmware and TPM capabilities differ across machines. In the diagnose stage, this action directly supports the required outcome: check eligibility before forcing an unsupported OS build.
Incorrect Answers
A:
Inspect hardware model consistency and PXE/network reachability. That step targets network imaging deployment when individual USB installations are inefficient and inconsistent. The current situation instead says firmware and TPM capabilities differ across machines, and the goal is to check eligibility before forcing an unsupported OS build.
C:
Determine backup completeness and installation media authenticity. That step targets clean installation versus upgrade when unknown software persists and system files cannot be trusted. The current situation instead says firmware and TPM capabilities differ across machines, and the goal is to check eligibility before forcing an unsupported OS build.
D:
Check firmware boot mode and existing partition scheme. That step targets GPT and UEFI installation when the installer is booted in legacy mode and will not use the intended layout. The current situation instead says firmware and TPM capabilities differ across machines, and the goal is to check eligibility before forcing an unsupported OS build.
Question 47
At Juniper Industrial, a desktop cannot enable a newer Windows release. Evidence: Firmware and TPM capabilities differ across machines. The support goal is to check eligibility before forcing an unsupported OS build. Which corrective or preventative action best addresses this requirement while retaining appropriate access and change controls?
- Upgrade eligible models and plan replacement for unsupported models
- Use supported upgrade media with backup and rollback plan
- Carry out a clean install after preserving user data and licensing
- Boot approved media in UEFI mode and initialize GPT after backup
Explanation
Correct Answer
A:
Upgrade eligible models and plan replacement for unsupported models. The case states that firmware and TPM capabilities differ across machines. In the design stage, this action directly supports the required outcome: check eligibility before forcing an unsupported OS build.
Incorrect Answers
B:
Use supported upgrade media with backup and rollback plan. That step targets in-place upgrade continuity when installed business apps and profiles should remain intact. The current situation instead says firmware and TPM capabilities differ across machines, and the goal is to check eligibility before forcing an unsupported OS build.
C:
Perform a clean install after preserving user data and licensing. That step targets clean installation versus upgrade when unknown software persists and system files cannot be trusted. The current situation instead says firmware and TPM capabilities differ across machines, and the goal is to check eligibility before forcing an unsupported OS build.
D:
Boot approved media in UEFI mode and initialize GPT after backup. That step targets GPT and UEFI installation when the installer is booted in legacy mode and will not use the intended layout. The current situation instead says firmware and TPM capabilities differ across machines, and the goal is to check eligibility before forcing an unsupported OS build.
Question 48
At Mountainview Realty, a desktop cannot enable a newer Windows release. Evidence: Firmware and TPM capabilities differ across machines. The support goal is to check eligibility before forcing an unsupported OS build. Which bounded nonproduction test best checks the proposed solution before wider deployment?
- Upgrade one pilot computer with sample line-of-business apps
- Run the vendor compatibility checker on sample machines
- Set up a golden image to several disposable lab endpoints
- Reimage an isolated test PC and restore mock user files
Explanation
Correct Answer
B:
Run the vendor compatibility checker on sample machines. The case states that firmware and TPM capabilities differ across machines. In the pilot stage, this action directly supports the required outcome: check eligibility before forcing an unsupported OS build.
Incorrect Answers
A:
Upgrade one pilot computer with sample line-of-business apps. That step targets in-place upgrade continuity when installed business apps and profiles should remain intact. The current situation instead says firmware and TPM capabilities differ across machines, and the goal is to check eligibility before forcing an unsupported OS build.
C:
Deploy a golden image to several disposable lab endpoints. That step targets network imaging deployment when individual USB installations are inefficient and inconsistent. The current situation instead says firmware and TPM capabilities differ across machines, and the goal is to check eligibility before forcing an unsupported OS build.
D:
Reimage an isolated test PC and restore mock user files. That step targets clean installation versus upgrade when unknown software persists and system files cannot be trusted. The current situation instead says firmware and TPM capabilities differ across machines, and the goal is to check eligibility before forcing an unsupported OS build.
Question 49
At Cedarbridge Health, a desktop cannot enable a newer Windows release. Evidence: Firmware and TPM capabilities differ across machines. The support goal is to check eligibility before forcing an unsupported OS build. Which result would most convincingly show the support requirement has been satisfied?
- Applications and user profiles remain usable after the update without data loss
- Clients receive distinct identities and required drivers
- Only supported devices proceed and backup is intact
- No old unauthorized application remains after installation
Explanation
Correct Answer
C:
Only supported devices proceed and backup is intact. The case states that firmware and TPM capabilities differ across machines. In the validate stage, this action directly supports the required outcome: check eligibility before forcing an unsupported OS build.
Incorrect Answers
A:
Apps and profiles work and update completes without data loss. That step targets in-place upgrade continuity when installed business apps and profiles should remain intact. The current situation instead says firmware and TPM capabilities differ across machines, and the goal is to check eligibility before forcing an unsupported OS build.
B:
Clients receive distinct identities and required drivers. That step targets network imaging deployment when individual USB installations are inefficient and inconsistent. The current situation instead says firmware and TPM capabilities differ across machines, and the goal is to check eligibility before forcing an unsupported OS build.
D:
No old unauthorized application remains after installation. That step targets clean installation versus upgrade when unknown software persists and system files cannot be trusted. The current situation instead says firmware and TPM capabilities differ across machines, and the goal is to check eligibility before forcing an unsupported OS build.
Question 50
At Pinecrest Logistics, a desktop cannot enable a newer Windows release. Evidence: Firmware and TPM capabilities differ across machines. The support goal is to check eligibility before forcing an unsupported OS build. What operational signal should the support team monitor for regression or a return of the issue?
- Watch redeployment errors and restore failures
- Track unsupported hardware and blocked feature updates
- Monitor imaging failures and duplicate identifiers
- Monitor firmware boot entry changes
Explanation
Correct Answer
B:
Track unsupported hardware and blocked feature updates. The case states that firmware and TPM capabilities differ across machines. In the monitor stage, this action directly supports the required outcome: check eligibility before forcing an unsupported OS build.
Incorrect Answers
A:
Watch redeployment errors and restore failures. That step targets clean installation versus upgrade when unknown software persists and system files cannot be trusted. The current situation instead says firmware and TPM capabilities differ across machines, and the goal is to check eligibility before forcing an unsupported OS build.
C:
Monitor imaging failures and duplicate identifiers. That step targets network imaging deployment when individual USB installations are inefficient and inconsistent. The current situation instead says firmware and TPM capabilities differ across machines, and the goal is to check eligibility before forcing an unsupported OS build.
D:
Monitor firmware boot entry changes. That step targets GPT and UEFI installation when the installer is booted in legacy mode and will not use the intended layout. The current situation instead says firmware and TPM capabilities differ across machines, and the goal is to check eligibility before forcing an unsupported OS build.